| Project Budgets:
				33,000 Building Gross Square Feet$15.44 Million Project Budget Funding:
				Bond Measure S (Ex. B #43): $22.476 Million Schedule:
				Design: 06/2008 (Completed)Bid/Award: 12/2009 (Completed)Construction (to be completed): 06/2012  (Completed) Architect: |  |