| Project Budgets:
				7 Acre Total Site Development$1.6 Million Project Cost Funding:
				Bond Measure S (Ex. B #55) Schedule:
				Design: 02/2004  (Completed)Agency Review: 03/2004 (Completed)Bid/Selection: 03/2004  (Completed)Construction: 09/2004 (Completed) Architect: |  |